Decathlon India Malur
Karnataka’s first platinum-certified warehouse
Grade A+ specification warehouse – built-to-suit warehouse 1,000,000 sq. ft. potential development,
including warehouse, office, and infrastructure.

1
The project stands out for its scale, complexity, and seamless execution, setting a benchmark for logistics and industrial parks in the region. It’s a testament to our expertise as an EPC contractor for industrial projects. By combining innovation, quality, and sustainability, we delivered a facility that meets global standards and supports long-term economic growth.

2
The warehouse boasts
Grade A+ specifications and is
certified Platinum by IGBC.
2-hour fire-rated AAC block concrete walls were used throughout the warehouse to enhance passive fire protection, ensuring compliance with fire safety norms while contributing to thermal efficiency and acoustic performance.

3
The project adheres to leading fire protection standards, including NFPA and FM Global guidelines, meeting the compliance requirements of insurers.

4
Sustainable practices were implemented, including a glass façade and a sensor-based lighting system.

5
FM2 flooring with on-floor robotic
logistics capability.

6
Rooftop solar panels to support energy sustainability.
Sustainability Initiatives
This project integrates future-ready and eco-efficient systems across all aspects:
Challenges Faced
COVID-19 Second Wave
- 45-day lockdown restricted site activity
and labour movement - Limited contractor mobilization: in-situ worker housing enabled continuity at reduced speed
Material Supply Crisis
- Steel shortage delayed PEB structural works
- Post-lockdown cost escalations pressured project budgets
Despite these, Conservve Buildcon chose to absorb cost fluctuations to stay committed to client timelines.
Execution Strategy & Project Management
Planning & Coordination:
Project charter developed to define scope, timelines, and deliverables.
Integrated project schedule with package-wise tracking.
Regular weekly client/vendor reviews, documented with MoMs.
Kick-off meetings to align contractors on quality, safety, and approvals.
Proactive design validation to prevent compliance rework.
Evaluation and Results
Despite the hurdles, the project reached practical completion in November 2021, recording only a 15-day effective delay, an impressive outcome in fast-track industrial project execution, especially when compared to industry norms during the pandemic.
Project Outcomes
What We Delivered
The Decathlon India warehouse at Malur showcases our capability to deliver landmark industrial infrastructure under challenging conditions. With a commitment to quality, sustainability, and precision execution, the project reflects our philosophy: We Construct to Save. In a post-pandemic era where resilience, compliance, and sustainability are nonnegotiable, this facility is not just a warehouse – it is a model of modern, intelligent, and future-ready industrial construction.
Award & Recognition

IGBC PLATINUM Certification
Next Case Study
The Kolkata CFS case study